Documents/FAQs

Application Accepted for Examination 

Latest Update: The Planning Inspectorate officially accepted the development consent application for the Helios Renewable Energy Project for a solar farm and battery energy storage system in North Yorkshire. The project will now proceed to the Pre-Examination and Examination phases.

Given the project’s scope, it is being reviewed under the Nationally Significant Infrastructure Project regime. The Planning Inspectorate will thoroughly examine the plans and, following a public examination process that includes dedicated hearings, will make a recommendation to the Secretary of State for Energy Security and Net Zero on whether to approve or refuse the application. The Secretary of State will then issue the final decision.

With the application now accepted, all related documents are available to the public on the Planning Inspectorate’s website. Members of the public interested in participating in the Examination process can register their interest through the Planning Inspectorate’s website at the link below: https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010140

The deadline for representations to be made is 30 September 2024.

Project documents

PLEASE NOTE: This page contains all relevant documents and information consulted upon prior to submission of the application for development consent. Please note that documents contained on these pages are now historic documents, and retained here for reference purposes.

Following submission, all the latest documents and information is contained on the Planning Inspectorate website: https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010140

All future updates and new documents will be published directly on the Planning Inspectorate website.

Statutory Consultation Documents - 26 October to 7 December 2023

Consultation Documents - Overview

PEIR Volume 1 - Non Technical Summary (NTS)

PEIR Volume 2 - Main Text

PEIR Volume 3 - Appendix

Volume 3 Cover Page

Appendix 1.1 – Statement of Expertise

Appendix 2.1 – Scoping Report

Appendix 2.2 – Scoping Opinion

Appendix 2.3 – Qualitative Dust Assessment

Appendix 2.4 – Phase 1 Ground Conditions Assessment (Part 1)

Appendix 2.4 – Phase 1 Ground Conditions Assessment (Part 2)

Appendix 2.5 – Solar Photovoltaic Glint and Glare Study

Appendix 3.1 – BESS Safety Management Plan

Appendix 4.1 – Opportunities and Constraints for Site Selection

Appendix 5.1 – Outline CEMP

Appendix 6.1 – Cultural Heritage Technical Appendix

Appendix 6.2 – Archaeological Mitigation Strategy

Appendix 6.3 – ASWYAS Geophysical Survey

Appendix 6.4 – Email Correspondence with NYC Conservation Officer

Appendix 6.5 – Correspondence with the NYC Archaeologist 1 of 3

Appendix 6.6 – Correspondence with the NYC Archaeologist 2 of 3

Appendix 6.7 – Correspondence with the NYC Archaeologist 3 of 3

Appendix 7.1 – LVIA Methodology

Appendix 7.2 – Viewpoint Correspondence

Appendix 7.3 – Landscape Effect Table

Appendix 7.4 – Site Appraisal Photographs

Appendix 7.5 – Representative Viewpoints

Appendix 7.6 – Visual Effects Table

Appendix 7.7 -Visualisations (see Visualisations section below)

Appendix 8.1 – Habitats and Desk Study Baseline Report

Appendix 8.2 – Ornithological Survey Report

Appendix 8.3 – Otter and Water Vole Report

Appendix 8.4 – Confidential Badger Report (Abridged Version)

Appendix 8.5 – Amphibian Baseline Report

Appendix 8.6 – Aboricultural Impact Assessment

Appendix 9.1 – Flood Risk Assessment and Appendices

Appendix 9.2 – LLFA Consultation

Appendix 9.3 – IDB Consultation

Appendix 9.4 – EA Consultation

Appendix 11.1 – Time History and Statistical Analysis Graph

Appendix 11.2 – Correspondence with Selby District Council Environmental Health Officer

Appendix 11.3 – Traffic Flow Data

Appendix 12.1 – Helios Traffic Flows

Appendix 12.2 – Helios EFT

Appendix 12.3 – Helios Carbon Calculations

Appendix 12.4 – Mean Air Temperature Anomaly

Appendix 12.5 – Average Annual Precipitation Anomaly

Appendix 12.6 – Maximum Summer Temperature Anomaly

Appendix 12.7 – Summer Precipitation Anomaly

Appendix 12.8 – Minimum Winter Temperature Anomaly

Appendix 12.9 – Winter Precipitation Anomaly

Appendix 12.10 – Annual Cloud Anomaly

Appendix 14.1 – ALC Report

Appendix 14.2 – Farm Reports

Appendix 14.3 – Outline Soil Management Plan

Appendix 14.4 – Note About UK Agriculture

 

(PEIR Appendix 7.7) - Visualisations

Informal Consultation: Phase 1 - July 2022

The consultation materials for the Phase 1 informal consultation (Summer 2022) are listed below (please note, these documents are now superseded with the statutory consultation materials listed above):

Frequently Asked Questions

What are we proposing to develop?

We are proposing to develop a solar farm with a battery energy storage system and associated infrastructure on land west of Camblesforth and north of Hirst Courtney in North Yorkshire.

The proposed solar farm would provide renewable electricity for distribution to the National Grid via a connection to the Drax National Grid 132Kv Substation, adjacent to Drax Power Station.

The proposal would generate a significant amount of energy each year of the proposed 40-year operational life, while also providing large CO2 savings when compared to generation of electricity by non-renewable sources, moving us closer to net zero.

In response to the feedback we received during our earlier consultation in 2022, we have developed a new Site Layout, which has reduced the overall footprint of the site (from 757 hectares to 476 hectares) and identified specific areas for landscaping and biodiversity net gain areas, helping screen the solar panels, encourage pollinators and improved local wildlife habitats.

Who is the applicant?

The applicant is Enso Green Holdings D Limited. Enso Green Holdings D Limited is a joint-venture partnership between Enso Energy and Cero Generation.

Enso Energy is one of the UK’s most experienced renewable energy developers, with an unparalleled focus on solar energy.

Cero Generation is a leading solar energy company, working across Europe to support the transition to a net-zero future.

You can find out more about Enso Energy and Cero Energy by visiting: https://ensoenergy.co.uk/

Where is the site?

The site is located south-west of Camblesforth, which lies southeast of Selby, and to the west of Drax Power Station. The southern parts of the site lie to the north of the village of Hirst Courtney. The cable route corridor extends to the east of Drax Power Station.

A site plan can be found here.

 

 

Why here?

One of the key drivers for siting renewable energy projects is being close to a suitable connection point to export power to the National Grid. A point of connection to the National Grid at Drax Power Station has been agreed, and the land identified for the project has been refined following a site selection process.

What are the impacts on the local environment and biodiversity?

A well-designed solar farm provides many opportunities for local ecological and biodiversity improvement particularly on land that has previously been intensively farmed. Potential biodiversity enhancements include reinforcement of existing and planting new hedgerows, planting of native grasses and wildflowers within and around the solar farm itself.

Further detailed information about the proposed biodiversity enhancements can be found on the Landscape Strategy Plan and consultation materials.

Will the impacts to agricultural land be taken into consideration?

Yes. As noted above, one of the key influences on where a project like can be be built is the proximity to an available grid connection. Understanding the nature and quality of the land (Agricultural Land Classification – ALC) within the site is an important assessment that we have undertaken as we have progressed the scheme design.

For context, the latest agricultural land statistics* (DEFRA, 2021) state that in 2021, there was just over 8.8 million hectares of utilised agricultural land in England. A recent publication by the Conservative Energy Network (CEN) states that ‘Currently, 0.08% of all land is taken up by solar farms.

This would only increase to just under 0.4% if we managed to increase solar coverage to 70GW of capacity, which the Energy Security Strategy stated as the target for 2035.

This is the equivalent of less than one third of the land currently occupied by golf courses across the United Kingdom’.** 

The solar panels will be fixed to the ground on fully removeable piled frames which will be removed in the decommissioning phase. There are areas within the site where fixed equipment is proposed which will, for the purpose of assessment, be considered as permanent development. These make up less than 3% of the site. The ALC grading and quantum of these areas has been considered and the significance of the loss assessed against the methodology in IEMA’s “A New Perspective on Land and Soil in Environmental Impact Assessment” (2022). A Soil Resource Plan, as necessary tied in with a Soil Management Plan, can be used to avoid or reduce the impacts on agricultural land.

*Available at: https://www.gov.uk/government/statistics/farming-statistics-land-use-livestock-populations-and-agricultural-workforce-as-at-1-june-2021-england Accessed in May 2022.

**https://www.cen.uk.com/our-blog-list/2022/6/1/how-harnessing-the-sun-can-help-secure-our-energy-and-food-supplies Accessed June 2022

Will the project mean that the existing footpaths and rights of way will be closed?

No. Existing rights of way will remain accessible during construction and operation. The scheme will be designed around existing public rights of way (PROW) so as to avoid any long term diversions or changes to these routes.

In addition, we have proposed to include a new permissive footpath within the proposals to improve pedestrian connections between Camblesforth and Carlton.

Will the proposals cause an increase in flood risk locally?

Solar panels are mounted on frames which are driven into the ground, meaning that dispersal of rainwater can continue. Where more permanent bases are required (such as for the transformers and energy storage facility) extensive assessment will be undertaken, with mitigation provided to ensure that there is no net increase in flood risk.

The Environmental Impact Assessment (EIA) work will need to demonstrate that we have undertaken extensive assessment of drainage and flood risk, and put in place any mitigation measures to ensure that there is no net increase in water runoff from the site.

Further information about our assessment of flood risk can be found in Chapter 9 of the PEIR documents here.

Will the solar panels be visible from my house?

Visibility of the site from surrounding areas has been a key design consideration.

To assess what the proposed scheme would look like, a Landscape and Visual Impact Assessment (LVIA) is being carried out as part of the EIA. This gives information on the design of the scheme and will identify key areas where visual and landscape mitigation (such as planting) is required.

The solar panels will be fixed to the ground on piled frames which will be fully removed in the decommissioning phase.

The panels will sit no higher than 3 metres from the ground, which, given the flat nature of the surrounding land, means that many will be screened from view from existing hedgerows, through enhancing existing hedgerows or planting new ones.

An assessment of various viewpoints around the site has been undertaken, with visualisations to help show what the site would look like from locations around the site. These can be viewed in Appendix 7.7 of the PEIR on the Documents/FAQ page.

Will panels cover the whole area?

No. There will be lots of green space all over the site. There will be gaps between each row of solar panels which will remain grass, and grass will grow underneath each row of panels.

Existing hedgerows and trees will be maintained, with buffers to allow for landscaping and there will also generally be at least five metres of open field space between security fencing and solar panels throughout the whole site. There will also be new areas of wild meadow planting, new trees and hedgerows will be planted, and there will be farm-style tracks to facilitate maintenance between the parcels of land.

Further details of the approach to planting and screening is contained in Chapter 7 of the PEIR.

When the panels reach the end of their life, will the land be deemed ‘brownfield’ making it easier to build on in future?

No.  The planning approval will require the site to be fully decommissioned and returned to agricultural use at the end of the project life. This application will not change the classification of the land.

Will these proposals cause additional traffic through Camblesforth, Hirst Courtney, Carlton and surrounding villages?

The Project have been consulting closely with the traffic management teams at North Yorkshire Council on local construction routes.

The anticipated average number of HGV deliveries would be 36 per day (18 arrivals and 18 departures) across the 12 month construction period. At its peak, 52 HGV movements are expected (26 arrivals and 26 departures).

The suitability of these routes will be confirmed by detailed on-site assessment and traffic surveys and agreed with North Yorkshire Council and National Highways.

Our traffic assessments show that there is likely to be very little impact on the local road network. However, a Construction Traffic Management Plan (CTMP) will be prepared to outline specific points, such as delivery times, restrictions, and routes to ensure that construction traffic does not have a detrimental impact to the local road network. An Outline CTMP will be available to review within the Environmental Statement, as part of the main DCO application.

 

Who will decide whether or not this Project receives planning permission?

Due to the nature of the proposed Project, an application to the Planning Inspectorate will be submitted under the Nationally Significant Infrastructure Project (NSIP) regime (Planning Act 2008) in 2023.

NSIPs are major infrastructure projects such as new harbours, roads, power generating stations (such as larger scale solar farms) and electricity transmission lines, which require a type of consent known as ‘development consent’ under procedures governed by the Planning Act 2008.

Development consent, where granted, is made in the form of a Development Consent Order (DCO).

Anybody wishing to construct an NSIP must first apply for consent to do so. For such a project, the Planning Inspectorate examines the application and will make a recommendation to the Secretary of State for Business, Energy and Industrial Strategy, who will make the decision.

Further information about the process can be found here.

How will the proposed project benefit the local community?

This scheme represents an important contribution to meeting the UK’s legally binding target under the Climate Change Act 2008 to achieve a ‘net zero’ carbon by 2050.

Renewable energy developments deliver secure supply of low carbon electricity for local communities and the wider population that is generated domestically using the UK’s natural resources. Solar power represents a ‘clean’ source of energy as it does not release any harmful emissions or pollutants.

Solar energy is also one of the cheapest forms of power generation in the UK and, in the future, can deliver lower energy bills for consumers by reducing the UK’s energy market’s reliance on foreign energy imports. This will help ensure a secure energy supply for future generations.

In addition, local benefits include:

  • Local jobs and investment – we are committed to using local labour and contractors wherever we can throughout the construction and ongoing operational life of the project.
  • Potential biodiversity enhancements including reinforcement of existing hedgerows and the planting of new hedgerows, native grasses and wildflowers within and adjacent to the solar farm itself.
  • Maintenance and enhancement of footpaths throughout the site as well as identified additional permissive footpaths to improve connectivity in the local area.
  • Community Benefit Contribution – A contribution to a community benefit fund is being considered to assist with local schemes, initiatives, and worthy causes. Through the consultation process, we are also keen to hear about any other potential local benefits that we could facilitate or deliver directly.

 

When will an application be submitted?

We are currently aiming to submit an application to the Planning Inspectorate in 2024.

When will the statutory consultation take place?

Informal consultation took place in July 2022 in the lead up to the statutory consultation process taking place between 26 October and 7 December 2023.

The website contains details about how to provide your comments (via an online form, freepost or freephone) and will be regularly updated over coming weeks. Further information can be found here.

How can I contact the Project Team to find out more and provide my comments?

You can get in touch with us in a number of ways. The website is the best place to start: www.helios-renewable-energy-project.co.uk. You can also email us at [email protected]. We have an online comment form to provide your comments or ask any questions.

We also have a freephone number (0800 0699 0081). If you wish to write to us, you can post to ‘FREEPOST TC CONSULTATION’ (no further stamp or address required).